Major improvements coming to Marystown Road

Post Date:08/26/2024 6:00 am

The City of Shakopee is in the planning stages of making improvements to Marystown Road and Adams Street between 17th Avenue and 12th Avenue, near Highway 169. 

The existing street and intersection designs are in need of safety improvements to help prevent crashes. The project will include reconstruction of Marystown Road into a two-lane divided roadway with single lane roundabouts at Vierling Drive, the Highway 169 North ramp and the Highway 169 South ramp intersections.

The City also plans to add pedestrian trails along the road, including additions to the existing bridge deck to improve pedestrian mobility. Construction is expected to begin in 2025 and will continue into 2026.

Through reconstruction, this hub of development and growth in Shakopee will see improvements in traffic safety, operations, pedestrian and bicycle safety, and provide the blueprint for future growth along the corridor for residential and business areas.

To stay up to date on the project plans and timeline, visit www.marystownroad.com.


Tentative Construction Timeline

Fall 2024 to Spring 2024 – Complete the final design plans and staging

Early 2025 – Present staging options to stakeholders and public for feedback

Late Summer 2025 – Public informational open houses prior to construction

Early Fall 2025 – Begin construction

Winter 2025/2026 – Construction suspended for season

Spring 2026 to Fall 2026 – Construction continues

Late 2026 – Project complete and open to traffic