The City of Shakopee plans to construct a multi-lane roundabout at the intersection of Eagle Creek Boulevard and Vierling Drive in 2024. The improvements are proposed to address traffic safety and operational needs from nearby developments that were identified in the Canterbury Commons Areawide Transportation Study. The project will include:
- Construction of a hybrid roundabout, featuring differing lane configurations on each leg based on traffic need
- Utility and stormwater management improvements
- Landscaping and roadway lighting
- Pedestrian trail and sidewalk improvements
- Flashing Emergency Vehicle Warning Signs notifying drivers of incoming Fire Trucks
- Overhead Utility replacement underground
Construction of the improvements will require a complete closure of the intersection, from June to August, to avoid coinciding with the school year. During the closure, traffic will be detoured along Mystic Lake Drive, 17th Avenue and Marschall Road. Local access will be permitted for adjacent properties located within the project limits.
Project Location
Detour Map
View a map of the Detour Plan here [PDF].
Project Schedule
- Begin Tree Clearing: Mid to late March 2024
- End Tree Clearing: 3-5 days after beginning, no later than March 31, 2024
- Road work (No Full Road Closure): May, 1, 2024
- Road / Intersection Closure: June 7, 2024
- Begin Roundabout Construction: June 10, 2024
- Roads Open / Substantial Completion: August 30, 2024
- Full Project Completion: November 1, 2024